Tojo Mushroom was looking to save costs and reduce their carbon footprint.
Energy Efficient Technologies performed a detailed energy audit, made numerous recommendations for improvements.
The purpose of this case study is to provide the results of the savings validation pilot of an HVAC and refrigeration ECM now known as CryoGenX4 at the largest mushroom growing facility in the US
Operation of the Mushroom House
Each HVAC unit used for conditioning the mushroom house operates on a unique schedule of set points, percentage of outside air, backup A/C, and heat at 100% while A/C is on. This schedule is important as the operation of the equipment affect the results of the test.
Data Analysis
The data was analyzed by gathering the operation schedule of each unit and categorizing similar settings of set point, outside air percentage, and outside temperature. Using multiple similar days the percentage of savings before and after were created and averaged to present a final value.
Other Food Manufacturing Case Studies:
In Logan Township, NJ, Dr. Schar owns and operates a 50,000 sq. ft. industrial bakery that requires large quantities of energy to precisely control the mixing, rising, baking and freezing of its...
HVAC Optimization, Now in its 4th patented generation called CryoGenX4, was validated in two stores. Total system efficiency across all five units improved by an average of 29%, while the EER across...
Marriott Residence Inn Miami Airport Detailed baseline and post measurements were taken of six (6) nominal 10-ton, 4-yr old AAON Roof Top Heat Pump Units (RTUs) serving the hotel. The primary purpose...
Energy Efficient Technologies
400 East Pratt Street, Suite 800
Baltimore, MD 21202
800-344-8132 (Office)